Site Meeting 05/05/09
Attended the first site Meeting on 05/05/09. Not surprisingly, many issues are yet to be ironed out. The electricity supply from SESB is just one of the few pending issues. M& E issues are also pressing. The original plan of handing over all 6 floors on 31/5/09 has to be extended till mid June.